Basic 4 · Physical Education · Healthy Diet
Building Endurance
In this topic you will discuss how longer physical activity increases endurance.
By the end of these notes you should be able to:
- Explain endurance
- Describe how regular long activity builds endurance
- Plan a simple endurance programme
What you already know
- Heart rate and aerobic fitness
Copy everything that has a blue line on its left into your notebook. The other parts are for reading.
- Strand
- Physical Fitness
- Sub-strand
- Healthy Diet
- Indicator
- B4.4.1.4.2 – Discuss how prolong physical activity increases endurance allowing movement to occur for longer periods of time
Introduction
When Kojo started jogging, he could only run for 2 minutes. After six weeks of practice, he could jog for 15 minutes. His endurance improved.
1. What is Endurance?
Endurance: The ability to keep doing an activity for a long time without getting too tired.
| Type | Meaning | Activities |
|---|---|---|
| cardiovascular | heart and lungs keep working | jogging, skipping, swimming |
| muscular | muscles keep working | push-ups, curls, squats |
2. How Endurance Improves
- The heart becomes stronger and pumps more blood with each beat.
- The lungs take in more oxygen.
- Muscles get used to working longer.
- Recovery after exercise becomes quicker.

3. Simple Endurance Plan
| Week | Activity |
|---|---|
| 1 | jog 3 minutes, walk 2 minutes, repeat twice |
| 2 | jog 5 minutes, walk 2 minutes, repeat twice |
| 3 | jog 8 minutes non-stop |
| 4 | jog 10 minutes non-stop |
Tip: Eat healthy food and drink water to support your training.
New words
- endurance
- The ability to keep going for a long time.
- cardiovascular
- About the heart and blood vessels.
- recovery
- Getting back to normal after exercise.
- progress
- Getting better over time.
- training
- Regular practice to improve.
- stamina
- Another word for endurance.
Summary
- Endurance is the ability to keep going for a long time.
- Regular, longer activity strengthens the heart, lungs and muscles.
- Increase activity time little by little.
- Good food and water support training.
Class activity: Endurance Tracker
- Jog or skip for as long as you can at a steady pace.
- Record your time on the activity record card.
- Plan to add one minute each week.
You need: Woven exercise mats, Local drum, Sticks of chalk
Exercises
Answer in your exercise book first, then check your answers.
1. The ability to keep going for a long time is…
- A. Endurance
- B. Speed
- C. Flexibility
- D. Balance
Show answer
Answer: EnduranceThat is endurance.2. Which activity builds cardiovascular endurance?
- A. Jogging
- B. Sleeping
- C. Sitting
- D. Watching TV
Show answer
Answer: JoggingIt works the heart and lungs.3. Getting back to normal after exercise is…
- A. Recovery
- B. Training
- C. Progress
- D. Pace
Show answer
Answer: RecoveryThat is recovery.4. Endurance improves with regular practice.
- A. True
- B. False
Show answer
Answer: TrueTraining builds endurance.5. Doing very long runs on the first day is the best way to build endurance.
- A. True
- B. False
Show answer
Answer: FalseIncrease gradually.6. Another word for endurance is ______.
Show answer
Answer: staminaThey mean the same.7. Give two ways the body changes as endurance improves.
Show answer
Answer: Any two: stronger heart, better lungs, muscles work longer, quicker recovery.The body adapts.8. Why should training time be increased gradually?
Show answer
Answer: To let the body adapt safely and avoid injury and exhaustion.Gradual progress is safe.
Homework
- Follow week 1 of the endurance plan at home.